Set A New Record For Construction Time in Shandong Province | The Steel Bridge Over The Beijing-Shanghai Railway Overpass On The Road Of Jinan Thermal Power Group

Aug 16, 2024 Leave a message

On August 15, the steel bridge of the Beijing-Shanghai Railway overpass on the entrance road of Jinan Thermal Power Group, which was built by the company, turned smoothly and turned 74 degrees clockwise in the air to achieve a "gorgeous turn", laying a solid foundation for the completion and opening of the whole line as scheduled.

 

It only took 180 days from the start of the project to the completion of the rotation, which set a new record for the construction time of steel box girder rotating bridge in Shandong Province.

 

news-5280-2970

The construction site of the Beijing-Shanghai railway overpass project is located in Gu Yunhu Street, Changqing District, Jinan City. The Angle between the bridge and the center line of Beijing-Shanghai Railway is 72 degrees, and the bridge deck is traizoid, 150 meters long and 26.237 meters wide. The rotating construction lasted 60 minutes, and the bridge turned 74 degrees clockwise and finally took place. The steel box girder of the rotating bridge has the characteristics of varying span, width and weight, etc. Due to the restrictions of transportation conditions, most sections of the steel box are assembled and welded on site, which is difficult to construct and requires high technology.

news-1080-608

In order to ensure the "accurate rotation" of the rotating bridge, the project department of the company, under the guidance of China Railway No. 10 Bureau, the owner unit and the company, conducted several site surveys, and carried out an 11° test rotation of the rotating bridge in advance on August 14, providing accurate parameters for the formal rotation and ensuring that the performance of the rotating system met the requirements of the rotating body.

 

Since the start of the project, the company's project department has made overall planning and precise deployment, formulated construction promotion plans, designated special persons to be responsible for the daily report on the construction progress, resolutely done the same day, constantly innovate to solve the technical problems in the process of rotation, and built high-quality projects.

 

The smooth rotation of the steel bridge across the Beijing-Shanghai railway overpass on the road entering the plant of Jinan Thermoelectric Group shows the company's professional strength and innovation ability in the field of bridge rotation technical services. The company will continue to adhere to the corporate mission of "building high-quality products and high-quality projects", and continue to explore and apply new technologies and new processes to contribute wisdom and strength to national infrastructure construction and regional economic development with more scientific and efficient services.